FREMONT, WI (October 2025) — While things may look a little quiet at the construction site of Fremont’s new Community Center and Neuschafer Library, progress is very much on track, and right on schedule.


Modern blue neuschafer library renderings for the village of fremont with solar panels, people in front. Cars parked nearby. Autumn trees in vibrant orange and red surround the area.

Crews have recently completed several major milestones, including pouring the concrete slab, finishing mechanical, electrical, and plumbing (MEP) underground systems, and completing all footings, backfills, and grading.


Right now, the concrete slab is curing, a necessary waiting period before the next phase of work begins.

“While the construction site has remained quiet the last couple of weeks, work will soon begin once again and rest assured, everything remains on schedule,” the library shared in their most recent update.

What’s Next

The next few months will bring visible progress as crews move into structural assembly. The glulam beams — large laminated timber supports that will form the frame of the building — are set for delivery in late October, with installation scheduled to begin in early November.


Once those are in place, construction will move forward quickly with roof panel installation, electrical conduit work, and interior systems over the winter months.


Modern Fremont Neuschafer Library renderings for Fremont WI community center with wooden interior; people browsing bookshelves and chatting. Bright lighting, colorful accent walls, relaxed atmosphere.

Tentative Neuschafer Community Library Construction Timeline

Item / Activity

Start

Finish

Status

Concrete Floor Slab

Sept. 15, 2025

Sept. 20, 2025

Completed

Glulam Delivery

Oct. 27, 2025

Oct. 29, 2025

Upcoming

Set Glulam Frame

Nov. 3, 2025

Dec. 1, 2025

Pending

Set Structural Roof Panels

Dec. 3, 2025

Dec. 19, 2025

Pending

Electrical Conduits & Boxes

Dec. 22, 2025

Jan. 9, 2026

Pending

A Community Effort

The Neuschafer Library and Village of Fremont expressed gratitude to the construction teams, stakeholders, employees, and community members who continue to support the project.


Group of people holding shovels at a sunny park for a new library groundbreaking. Banner reads "New Library Community Coming Soon."

A recent photo taken by Rebecca Doyle posted to Neuschafer Library page on September 15th shows the smooth, finished slab ready for framing — a strong foundation for what’s to come.


Construction site with gravel and concrete, excavator, and orange cones. Buildings with red and gray roofs in the background, under a blue sky.

This new facility will combine Fremont’s beloved Neuschafer Library with a multi-use community center, providing modern spaces for reading, learning, meetings, events, and programs for all ages.


Stay tuned for more updates as framing begins in November! Have a story you'd like to share? Email us at Events@weyauwegafremontnews.com! We'd love to hear from you!

Subscribe to our newsletter

Comments


Supported by

Blue and White Modern Snow Removal Services Banner (Instagram Post (45)).jpg
473628812_10233948449471436_7021255233679749042_n.jpg
bottom of page